Tenaska Project Expedition

Documents and meeting materials related to:

Substantial Accord (SA) 25:01 – Planning Commission Substantial Accord Review and Determination for Expedition Generation Holdings per Code of Virginia Section 15.2-2232

Zoning Text Amendment (ZTA) 25-09, a request to Amend the “Code of the County of Fluvanna, Virginia,” by amending height regulations for power production plants.

Special Use Permit (SUP) 25-04, a request by Expedition Generation Holdings to allow the construction of a gas-fired electric generation facility.

Past Meetings: 

  • Oct 7, 2025 Planning Commission meeting materials.
    • Planning Commission deferred ZTA 25-09 and SUP 25-04 until January 13, 2026. 
    • Planning Commission deferred SA 25-01 until November 18, 2025. 
  • Nov 11, 2025 - Board of Supervisors Meeting
    • Board of Supervisors authorized deferring the Substantial Accord 25-01 determination until the January 13, 2026 Planning Commission Meeting.  
  • January 13, 2026 Planning Commission meeting materials.
    • Planning Commission denied SA 25-01. 
    • Planning Commission deferred ZTA 25-09 and SUP 25-04 until February 24, 2026. 

Upcoming Meetings: 

  • Feb 24, 2026 Planning Commission Special Meeting
    • Unfinished Business: ZTA 25-09 & SUP 25-04
  • Mar 18, 2026 Board of Supervisors Regular Meeting and Public Hearings
    • Public Hearing: ZTA 25-09
    • Public Hearing: SUP 25-04 (Pending outcome of Planning Commission Meeting on Feb 24, 2026)
    • Action Item: It is anticipated that Board will consider the appeal of the Planning Commission's Jan 13, 2026 Substantial Accord determination during this meeting. 

Tenaska Power Generation/Expedition Generation Holdings LLC has provided an application overview and additional information on their proposed Tenaska Project Expedition electric generating facility. This information is related to SUP 25:04, SA 25:01, and ZMP 25:09, and is available in the documents below.